Siilinjarvi logo

Marking of the building site

Building control measurements

Marking the location and elevation of the building on the land

The building permit may stipulate that construction may not begin until the relevant municipal authority has marked the location and elevation of the building on the ground in accordance with the approved plans. The land marking and site survey required by the building permit shall be invoiced together with the building permit.

Marking the location and elevation of the building is carried out on the client’s order after the building permit has been issued. The marking is carried out by the surveyor’s office.

When placing your subscription order, be prepared to present:
– building permit number
– property identification number
– address of the building site
– site contact details

Depending on the work situation, delivery time is about 1-2 weeks. Please order your subscription well in advance.

Contact

Mapping Specialist

Risto Pääkkönen

Mapping Specialist

Sami Syri